top of page
Tioga Road and Tuolumne Meadows Parking – Yosemite National Park
Client
Steve Manning Construction, Inc.
Year
Location
Yosemite National Park, USA
Contractor
2021-Current
Professional Assurance and Testing, Inc. is providing quality control management, inspection, and
testing during construction of 12 miles of Tioga Road, including rehabilitation of 16 parking lots between
Olmstead Point and Gaylor Pit Road. Additionally, the mainline portion of the project includes
construction of two new precast box culverts along Tioga and Soda Springs Roads. The also project
includes cold recycling of the existing surface, placement of new asphalt at a depth of 3”, numerous
drainage improvements, and nearly 80,000 lineal feet of slip formed curb and gutter.
Construction Cost – 34 million
Steve Manning Construction, Inc.